Work Scope:
EPCM
2x 32.000m³ Ethylene Tank
2x 18.000m³ Ethane Tank
Engineering:
Detail Engineering including seismic dynamic analysis by Finite Element Method
Tank insulation
Process piping design and basic engineering Procurement
Prefabrication of Material
Delivery of material DAP Site
Construction:
Preparations of Inspection and Test Plan
Preparation of Hydrotest Procedure
Welding and quality plan
Erection manual
Site Supervision during complete Construction